Rotary drilling rig on Western Avenue in San Pedro being used to explore underground breach in tunnel that will house new wastewater pipes. (Photo Courtesy of Los Angeles County Sanitation Districts)
Map shows where bore holes are being drilled on Western Avenue in San Pedro. Workers send imaging equipment below ground to a depth of 370 feet to determine more about what caused the tunnel breach in a project to build new wastewater pipes from Carson to San Pedro. Work began in September 2025 on Western Avenue above where the underground breach occurred and was initially expected to take four to six weeks. The location is on Western Avenue across from the Fifth Street cul-de-sac. (Courtesy image)
A worker looks down the shaft to the tunnel of the Clearwater project site site in Wilmington on Thursday, July 10, 2025. Thirty-one workers, aided by rescuers, made it out safely after a stretch of tunnel under construction collapsed in Wilmington on Wednesday night, July 9, 2025. (Photo by Dean Musgrove, Los Angeles Daily News/SCNG)
Sonic drill rig on Western Avenue in San Pedro. The equipment is being used to explore a tunneling breach some 360 feet below ground that is being created to house new, larger wastewater pipes. (Photo Courtesy of Los Angeles County Sanitation Districts)
Clearwater breach collapse on July 9, 2025 in San Pedro. (Courtesy Clearwater Project)
Mile 5 of the Clearwater project runs south to the left of Western Ave. in San Pedro seen here on Thursday, July 10, 2025. Thirty-one workers, aided by rescuers, made it out safely after a stretch of tunnel under construction collapsed in Wilmington on Wednesday night, July 9, 2025. (Photo by Dean Musgrove, Los Angeles Daily News/SCNG)
A worker drives off a construction site property after a tunnel collapsed on dozens of workers in the underground Clearwater Tunneling Project in Wilmington on Wednesday, July 9, 2025. (Photo by Raphael Richardson, Contributing Photographer)
A worker drives off a construction site property after a tunnel collapsed on dozens of workers in the underground Clearwater Tunneling Project in Wilmington on Wednesday, July 9, 2025. (Photo by Raphael Richardson, Contributing Photographer)
LA County Sanitation Districts PIO Michael Chee speaks at a press conference after a tunnel collapsed on dozens of workers in the underground Clearwater Tunneling Project in Wilmington on Wednesday, July 9, 2025. (Photo by Raphael Richardson, Contributing Photographer)
Gaps in compacted filler grout, or cement, may have allowed water and debris to seep onto the steel lining tube of an under-construction wastewater tunnel, leading to instability, according to the key finding in an in-depth report about what caused the tunnel to breach on July 9, 2025, temporarily trapping workers underground and indefinitely stopping the ambitious, yearslong project.
Read more Orange County boys athlete of the week: Cyrus Aviles, Fullerton
The Clearwater Tunnel Project launched in 2019 and had proceeded with no issues. But nearing its final ending point, a tunnel breach occurred at the 5-mile mark under Western Avenue, in San Pedro. It trapped 31 workers who were subsequently rescued safely after they were able to climb over the top of a fallen sediment pile, where there was still space, and then walk to the entrance of the tunnel several miles north.
The more than $600 million project has been stalled since the breach occurred as investigators have tried to find out what went wrong.
The key finding in the more than 700-page-long “Hatch Report,” which was released on Friday, Nov. 13, points to gaps in compacted filler grout, which is packed in to encase the tunnel’s steel lining tube, allowing water and debris to seep, leading to the instability. That is now the center of what is anticipated to be a long and detailed process to safely resume work on the project, which was within only a mile of its final destination.
The independent report looked at the factors that caused the breach. It was produced by Hatch, an engineering consultant in Long Beach that was hired by the Los Angeles County Sanitation Districts, which had spent years designing, planning and executing the project to replace too-small wastewater pipes with larger underground infrastructure to carry water to the ocean. The older system remains intact and is still operational.
But for now, work on the new system is indefinitely paused.
“We have zero projections about when work can start again,” Sanitation Districts spokesperson Michael Chee said in a Friday phone interview.
The breach, which is some 394 feet beneath Western Avenue, just south of Weymouth Avenue, occurred when the infrastructure was only about a mile from its final destination at White Point/Royal Palms Beach in San Pedro.
The entrance to the tunnel is adjacent to the A.K. Warren Water Resource Facility on South Figueroa Street, north of Lomita Boulevard.
“Our hope was that we’d be having a celebration at the beach this past summer,” Chee said on Friday.
Read more San Juan Hills football overcomes rough start to beat Tustin
The incident has also sparked some legal maneuvering, with one worker filing a claim against the contractor the county hired to construct the tunnel. The sanitation agency tapped Flatiron Dragados to construct the tunnel. The Hatch report said apparent irregularities around the site were spotted by Flatiron in the days before the breach.
Warning signs were there, the Hatch report said, with signs of “deformation and stress.” The report determined that more aggressive measures should have been taken to reinforce the tunnel. The primary finding, the report said, was that the most likely cause was that not enough cement had been injected into the crevices in the beginning.
It has been determined that dirt, rocks and water have filled the impacted portion of the tunnel in the aftermath, with workers conducting efforts from above to remove the debris, captured in images using high-tech drone technology sent below the street’s surface over the course of several months.
“In retrospect,” Chee said Friday, “there was information that would have been helpful if certain facts were brought to our attention.”
Flatiron Dragados could not be reached for comment on Friday. The company is now conducting drone imagery below Western, beyond the breach site, where no other inspections have yet been done to determine what the condition is moving ahead, Chee said.
The condition of the project’s electrically powered tunnel boring machine is among the main concerns, as it still sits buried just ahead of the breach, he added.
“We assume it’s underwater,” Chee said. “I don’t think we’ve put any stake in the ground in terms of a timeline (for when work can restart). The primary focus is on safety.”
No surface movement has been detected along the pipeline’s route, he said, noting that surface monitors have been installed in the area to signal any issues at street level. The tunnel route was originally mapped so it would not pass under homes or structures but would follow beneath streets.
Read more Orange voters favor tax Measures I and J, but not charter proposal Measure K
The report was posted on the Sanitation Districts’ website late Friday.